W.O.R.K. - W.ILLPOWER O.RGANIZATION R.ESPECT K.NOWLEDGEW.O.R.K. Works!
HOME OUR MISSION ABOUT US HELP US CONTACT US FAQs




CONTACT W.O.R.K. A detailed breakdown of how all our raised money was spent building 7 houses.
W.O.R.K. 2006 EXPENDITURES
 
Description of expense Cost Cost % of Total
  (rupees) (US $) Expenses
Land purchase 1150000 11500 23.5
Jack tree purchase 170000 1700 3.5
Initial survey (perimeter) 10000 100 0.2
Excavation/levelling costs 61000 610 1.2
Falling costs 3300 33 0.1
Milling costs 5700 57 0.1
Extra lumber 10500 105 0.2
Tool purchases 25200 252 0.5
Materials 1922000 19220 39.2
Sri Lankan management 267500 2675 5.4
Sri Lankan labor 558100 5581 11.3
Van rental costs 87500 875 1.8
Diesel costs 33000 330 0.7
Drinking water 23900 239 0.5
Site security 45000 450 0.9
Electricity charges 3000 30 0.1
Worker bonuses 134000 1340 2.7
Account opening/closing 3500 35 0.1
Media video 2500 25 0.1
Well costs* 50000 500 1
Final survey* 20000 200 0.5
Transfer of final deed* 66000 660 1.3
Electrical hook-up* 250000 2500 5.1

Total 4901700 49017 100
 
*Costs not yet finalized        

 



EXPLANATION OF EXPENDITURES to APRIL 5

Land Purchase 1500000 rupees
The purchase price of 1 500 000 rupees for the land included the lawyer’s fee and the stamp cost. The land is located about 4 km inland from Galle. It is well drained and already had two existing wells on the site, one of which would require cleaning and refurbishing to make it useable again.

Jack Tree Purchase 170000 rupees
The jack trees would have been part of the land purchase but we originally thought they needed to be removed in order to build the houses. The landowner from whom we purchased the property had planned to log the trees himself prior to us beginning house construction and therefore, had deducted them from the purchase price. However, once we realized that none of the jack trees required cutting in order to build the houses, we opted to pay the owner the equivalent value he would receive for cutting the trees. There are only eight jack trees on the site but they possess very high timber value because of their excellent lumber qualities. We felt it was worth keeping the jack trees because they provided much-needed shade and a food source (jack fruit) for both the recipients and for the monkeys that regularly visit the site. The new recipients will also not be allowed to cut the jack trees, a rule enforced by the village headmen.

Initial Survey (Perimeter) 10000 rupees
The initial survey re-established the lot boundaries, which had last been surveyed in 1926.

Excavating/leveling costs 61000 rupees
A wheeled backhoe with a clam bucket on the front-end loader was hired to level the building sites and provide road access for materials delivery. Leveling also included the demolition of the decrepit old building which had been on the site from the time of the original survey. It also included the cost of a dump truck used to remove debris from the site. In total the excavator and truck were on the site for three days.

Falling costs 3300 rupees
A faller was hired to cut down trees that were an impediment to road and house construction. 1300 rupees of the total falling costs were spent on the removal of a single coconut tree by a specialized cutter after the construction of several houses. We had overlooked the need for this tree to be fallen in our initial assessment and bringing it down required a specialized faller to first climb the tree and remove the upper third with ropes and a hatchet. He received almost double the daily pay of a skilled mason for less than an hour’s work but anyone who saw the process transpire will attest to the fact that he easily earned his money!

Milling costs 5700 rupees
We utilized the wood from almost all of the trees which we needed to cut down. One was too rotten and several others were too small to have any value. But a crew arrived at the site with a portable sawmill and custom cut any useable timber to our specifications. We managed to get enough timber for scaffolding planks and a full set of forms for pouring the concrete ringbeams.

Extra lumber 10500 rupees
We could have managed with just the one set of forms we had milled from our own timber but it was well worth it to purchase extra lumber for a second set. Often, we were ready to pour a ringbeam on one house before the concrete was set on another one. Having two sets of forms allowed us to continue to move forward without delay.


Tool Purchases 25200 rupees

This number would have been significantly higher but for the generosity of some of our volunteers. Many thanks to Andy, Karen, Brent, Trudie, Shilpa, Brian and Jim, who all brought tools and supplies from home and insisted on donating them to the project. Among the tools we purchased locally, the circular saw proved to be the most invaluable, shaving significant time off the roof construction process.

Materials 1 922 000 rupees
By far our largest expenditure, the materials cost per house broke down as follows:
Cement 26500 rupees
Sand 35000 rupees
Concrete blocks 40500 rupees
Aggregate (gravel) 11000 rupees
Large blast rock 7500 rupees
Re-bar 3200 rupees
Roof rafters and beams 25000 rupees
Timber for doors and windows 67500 rupees
Roof tiles 35000 rupees
Locks and hinges 2000 rupees
Paint and whitewash 4000 rupees
Red floor cement 2000 rupees
Varnish 1500 rupees
Plumbing supplies 2000 rupees
Electrical supplies 11 500 rupees

There were a few additional minor costs but the above costs covered almost all of our materials expenditures.

Sri Lankan management 267500 rupees
Initially, we hired two Sri Lankan managers and one assistant manager for the site. They acted as translators, negotiators, supervisors and purchasers. After March 15, it became apparent that two managers was excessive, at which time we cut back to just one.

Sri Lankan labor 558100 rupees
The cost of Sri Lankan labor, particularly masons, is extremely cheap. A skilled mason normally receives the equivalent of about $6.00 US per day while a mason’s helper receives just $3.50 per day. We increased their respective wages to $7.50 and $4.50 per day, still exceptionally low for the value we received.
The breakdown between the various labor activities was as follows:
Masonry: 299100 rupees
Carpentry: 241500 rupees
Electrical: 17500 rupees

Van Rental Costs 87500 rupees
We rented two vans for most of the month of February when our volunteer numbers were at their maximum and just one van for the remainder of the time. The van cost ten dollars per day to rent.


Diesel Costs 33000 rupees

Diesel costs for the van were five dollars per day.

Drinking water 23 900 rupees
W.O.R.K. paid for people’s drinking water at the site. A five liter bottle of water cost 90 cents and an average person consumed about 2.5 liters of water per day.

Site security 45000 rupees
This expenditure was higher than what we had anticipated paying. Prior to our arrival, promises were made to a local neighbor by another aid organization working adjacent to our site. He had been promised a new home plus 60 rupees per day in return for watching over the site. The organization failed to live up to its commitments and we agreed to cover some of these for the man, whose family has been living in a make-shift lean-to carved out of the bank. We provided all of his renumeration in the form of materials to be used for his new home, thereby ensuring that the money was put to good use. A small portion of the total was used to provide materials for another neighbor who had also watched over the site periodically.

Electricity charges 3000 rupees
We paid the above amount in return for the use of a neighbor’s power supply to run the skill saw, electric drill, hand planer and sander.

Worker bonuses 134 000 rupees
We found that our masons were highly underpaid relative to their skills and to how hard they worked. Visiting their homes, we also quickly realized that many of them could not afford to live in homes any better than the tsunami victims we were housing. So we decided to provide them with bonuses. A number of volunteers also chipped in and helped them out on an individual basis.

Account Opening/Closing
The cost of opening and closing our local checking account in Galle.

Media video 2500 rupees
We needed to have some sort of formal documentation of our efforts. In Sri Lanka, this entails paying the local media to shoot video and write a short story in the newspaper.

Well costs 50000 rupees
At the time we left, the second well had been drained, cleaned out and fully refurbished. It would require one more draining and a purity test after we left.

Final survey 20000 rupees
This will entail dividing the area into individual lots for the respective recipients.

Transfer of final deed 66000 rupees
This process will take several months but is key to the successful completion of the project. Each property will be deeded to the youngest child in the family in order to ensure that the recipients are not able to sell it for at least a decade.

Electrical hook-up 250000 rupees
At the time we left, we still had not received an official estimate on the cost of putting in poles and three-phase wiring from the nearest source. The above amount was the final ‘guesstimate’ we received before leaving, an amount which would leave us 130000 rupees or 1300 US dollars short of completing the project.

 

 

 

 

 

 

 

 

Copyright 2005 W.O.R.K.  © 2006 W.O.R.K.